Between Crescent Drive and Reeves Drive, crews are building a landscaped median down the middle of Wilshire Boulevard. Metro's work notice calls it the "Wilshire Island." A block west, new trees are going into the north sidewalk between El Camino and Crescent, and shrubs are being planted in the median between Crescent and Beverly Drive. The concrete K-rail barriers that lined the curb lanes for years have mostly been replaced by cones and delineators.
Beneath all of that sits the Beverly Dr station, and it will not carry a passenger until spring 2027 at the earliest. On the city's east edge, Wilshire/La Cienega has been carrying riders since May. Starting Friday, October 23, it goes dark for ten days, partly so the station in the Golden Triangle can open. In Beverly Hills, the subway is being finished from the top down. The street comes back first, and the trains follow.
The Open Station Closes Friday, Partly for Beverly Drive
Wilshire/La Cienega opened on May 8, 2026, together with Wilshire/Fairfax and Wilshire/La Brea. According to Metro's announcement on The Source, all three stations close at 2 a.m. on Friday, October 23, and are scheduled to reopen at 4 a.m. on Monday, November 2.
Metro gives two reasons. Wilshire/La Brea opened on temporary electrical equipment, and the permanent equipment can only go in with the station's power shut off. Metro will also use the closure "to connect systems and complete other work needed for the next D Line extension to Beverly Hills and Century City." So part of those ten days goes toward the Beverly Dr station.
During the closure:
- D Line trains run only between Union Station and Wilshire/Western.
- A shuttle bus, Line 855, connects Wilshire/Western with all three closed stations every 10 minutes.
- Metro Bus Lines 20 and 720 keep their regular service along Wilshire.
- The Metro Art Culture Pass stays valid, and its perks run through April 30, 2027.
Weekend riders have a second schedule to watch. Starting October 10 and 11, the B and D Lines have been running every 20 minutes on select weekends while Metro installs communications systems and maintains track. Holiday weekends are excluded.
Beverly Dr Is 95% Built and Still Has Its Testing Ahead
The Beverly Dr station box runs under Wilshire from Cañon Drive to Beverly Drive. Its entrance is planned at the southwest corner of Wilshire and Reeves Drive, with crossings at Beverly Drive and at North and South Cañon Drive linking both sides of the boulevard to the Golden Triangle and Rodeo Drive.
Metro's August 2026 status report on Section 2 puts the work at 95% complete, with construction and systems work still going at Beverly Dr, at Century City/Constellation and in the tunnel. The same report shows why 95% does not mean almost open. Testing was still at the local field acceptance stage. Contractor system-integration testing, Metro testing with its Rail Operations Center, pre-revenue operations and revenue service were all still ahead on the critical path. Metro forecasts revenue service for spring 2027. In its station FAQ, the City of Beverly Hills gives the same timeline and notes that the date may change with Metro's schedule.
Inside the station, Metro's September 9 community presentation showed escalators and elevators being installed, glass mosaic panels being prepared, and walls along both sides of the trainway being prepared for art. According to the City, the station will have no new parking structure. Metro expects riders to use existing parking within a half-mile walk, and the City says CCTV-monitored bike lockers and bike hubs are planned for the station plazas.
Where the Street Work Is This Month
Since the station still needs months of testing, the surface work is what changes a Wilshire drive or walk this fall. Here is the October work on Metro's monthly look-ahead for Beverly Dr:
| Location | October work | What it means on the street |
|---|---|---|
| Wilshire, El Camino to Crescent | Trees planted on the north side | Brief lane reduction with flaggers during unloading; sidewalk detours |
| Wilshire median, Crescent to Beverly | Shrubs planted | Two lanes each way maintained |
| Wilshire median, Crescent to Reeves | New landscaped "Wilshire Island" median | Occasional one-lane reduction for concrete pours; flaggers help pedestrians near Crescent and Reeves |
| Maybourne alley, N. Cañon to Beverly at Wilshire | Asphalt demolition and restoration | Work hours may run 7 a.m. to 4:30 p.m. |
| South Reeves Drive | Driveway removed and rebuilt | May narrow to one lane with flaggers; sidewalk closures |
| Wilshire, El Camino to Camden | Curb, sidewalk and ADA ramp upgrades on both sides | Lane shifts and detours to the nearest crosswalks |
Lane rules are looser than they were in summer, but construction rules still apply. The look-ahead keeps two lanes each way on Wilshire between Beverly and Crescent during normal operations. Wilshire may drop to one lane each way from 9 p.m. to 7 a.m., and occasionally one side may narrow to a single lane between 9 a.m. and 4 p.m. South Beverly Drive may narrow to one lane each way from 9 a.m. to 4 p.m. and again from 8:15 p.m. to 7 a.m.
No full reopening date has been given. The City's September 2026 capital projects update says Wilshire "will be fully reopened once the remaining civil and utility work is complete." It also said sidewalk restoration on the north side of Wilshire east of Beverly Drive and east of North Cañon was expected to finish by the end of September, with more streetscape and hardscape work to follow. In early September, Beverly Press reported sidewalk and curb work around Sterling Plaza at Wilshire and Beverly.
For a construction issue that can't wait, the notice lists Metro's 24/7 hotline at 213.922.6934 and the City's Ask BH line at 310.285.1000.
At La Cienega, the Trains Came First and One Sidewalk Is Still Waiting
The east end of Wilshire shows the opposite order. Wilshire/La Cienega has been carrying riders since May, and its street-level work is still going. The City's September update says civil restoration and punch-list items such as traffic signals and push buttons will continue through fall 2026. Final resurfacing of Wilshire between Stanley Drive and San Vicente Boulevard, along with nearby stretches of La Cienega, Hamilton, Gale and Tower, was scheduled over weekends ending September 26. Beverly Press covered that final repaving and the lane reductions that came with it.
The longest-running item is one block of sidewalk. Permanent restoration on the south side of Wilshire between La Cienega and South Hamilton Drive "remains pending Metro's plan that meets the Secretary of the Interior's Standards," according to the City. The City also expects the northwest and southwest curb ramps at La Cienega and Wilshire, plus fiber restoration, to be finished by October. Soft lane closures during off-peak hours continue between Stanley and San Vicente.
Metro's September presentation also listed temporary replacement parking near the station, with one hour free from 10 a.m. to 3 p.m. on weekdays. One lot is at 8447 Wilshire, entered from North Hamilton, and the other at 8350 Wilshire, entered from South Tower.
The Money Followed the Longest Construction Zone
Metro's Business Interruption Fund gives grants to small businesses next to the rail corridor. To qualify, a business must have been in place for at least two years and have 25 or fewer full-time employees. Grants are capped at $60,000 per impact year, and with Section 1 open, Metro is awarding up to six months of grants for impacts that occurred during construction.
Metro's September presentation shows where the Beverly Hills money went, as of April 30, 2026:
| Station area | Amount awarded | Grants |
|---|---|---|
| Wilshire/La Cienega | $7,647,199 | 228 |
| Wilshire/La Cienega West | $4,896,780 | 135 |
| Beverly Drive Station | $456,090 | 10 |
| Beverly Hills total | $13,000,069 | 373 |
Grants for the two La Cienega areas total more than 25 times what went to the Beverly Drive station area. That is where the trains arrived first, and it is also where the work at street level has lasted longest. As the Golden Triangle's own station nears opening, that ratio is the baseline to compare against.
Metro's Eat Shop Play guide lists the businesses near the open station, and a shuttle stop during the closure is a reason to visit a few. Its "Eat Nearby" list for Wilshire/La Cienega includes Bombay Palace Beverly Hills, Boss Sushi, Continental Kitchen, Gourmando, Prospect Gourmand, Series A Coffee and Beverly Hills Liquor Wine and Deli. For errands, the guide lists Ella Judaica, Family Pharmacy of Beverly Hills, HEPPS Prescription Pharmacy, Jewels on Wilshire, San Wilshire Printing & Copies and the Beverly Hills Postal Center. Bodyline Pilates, Hot 8 Yoga, Pure Barre Beverly Hills and the Saban Theatre are listed nearby too.
What the Calendar Looks Like From Here
The order matters for anyone planning around Wilshire over the next year:
- October 23 to November 2: Wilshire/La Cienega closed, Line 855 shuttles running, and systems work for the Beverly Hills extension underway.
- Through fall 2026: Punch-list work near La Cienega, plus trees, the median and ADA work between El Camino and Reeves.
- Spring 2027: Metro's forecast for the Beverly Dr and Century City/Constellation stations to open.
- Fall 2027: Metro's forecast for Section 3 to Westwood/UCLA and the Westwood/VA Hospital, ahead of the 2028 Olympic and Paralympic Games.
Until then, the change between El Camino and Reeves is the one you can already see: cones in place of K-rail, trees going into the sidewalk, and a planted median being poured down the middle of Wilshire.
If you own along the Wilshire corridor or have been watching the Golden Triangle as the Beverly Dr opening approaches, I follow these blocks closely and am glad to talk through what the new station and the finished streetscape could mean for your property. Simon Mashian is here when you're ready. Let's Connect.